No. WBS No. Project Name Status Council
District
Work Orders NTP Cons. Award Date Cons. FY Est. Cons. Cost Remarks
1 M-410024-0001-3     Southland Area Drainage and Paving Improvements Subproject 1  Active  D    November 27, 2020 (Targeted)  N/A  2029   $0  [09/11/2026] This project is in the initial design phase, the Level of Effort for Professional Engineering Services is currently under negotiation which will be followed by RCA. The Design Phase-1 is anticipated to start in Fall 2026. 1st Public engagement meeting is expected to take place in July 2028
2 M-410041-0001-3     Wheeler and MLK Detention Basins, RR Culvert, and KG Expansion  Active  D,I    March 16, 2026 (Actual)  April 25, 2029 (Expected)  2028   $20,570,000  [09/04/2026] The project is currently in the early 30% design phase, with construction anticipated to commence in June 2029. The design contract was awarded on January 21, 2026. The first public engagement is planned to take place during Phase 2 of the design process.
3 M-410044-0001-3     Sunnyside Area Detention Basin  Active  D           $0  No current issues
4 M-420HUD-006A-3     DR15 6A Edgewood Park Detention Basin  Active  D    N/A  December 02, 2026 (Expected)  2027   $3,500,000  [9/3/2026] a) Current Milestone: Issued NOIA to the lowest bidder b) Upcoming Milestone: Construction RCA c) Progress Towards Completing Current Milestones: We received the fully executed contract on January 15, 2025. However, funding allocation delays caused the consultant to pause Phase II design work. After 6.5 months, the contract amendment is complete, and the first invoice has been processed. Work resumed again at the end of February 2025. Last public engagement was on September 11, 2025.
5 M-420HUD-013A-3     DR15 13A EP Hill Park Detention Basin  Active  D      March 26, 2027 (Expected)     $3,809,862  [09/04/2026] a) Current Milestone: Advertisement was issued on August 14, 2026. Pre-Bid Conference was held on August 26, 2026. b) Upcoming Milestone: Bid Opening: September 17, 2026 c) Progress towards completing current milestone: Submitted all the required pre-bid documents to SPD.
6 N-001037-0053-3     Citywide Overlay #13  Active  B,C,D,E,H,I,J,K  8  N/A  N/A  2009   $0  Design project is near completion. Utilizing Phase III services for last work order.
7 N-001037-0067-3     Citywide Overlay / Rehabilitation Project (FY2013)  Active  B,C,D,G,I,K  2  N/A  N/A     $0  No additional work orders will be assigned for design.
8 N-210004-0001-3     Cloverland Area Paving and Drainage Improvements  Active  D    September 25, 2015 (Actual)  April 28, 2027 (Expected)  2027   $23,701,000  [08/28/2026] The Notice to Proceed (NTP) was issued on March 12, 2026, to revise the 90% design submittal, originally based on pre-Atlas 14 drainage criteria, to meet current Atlas 14 requirements. EOR resubmitted 90% on 8/15/26. 90% sent for review 8/28/26. Two variances are submitted for review by MSD and SWO. MSD has approved their variance; and it has been sent to OCE for their review. Utility companies are reporting no conflicts with the exception of CNP Streetlighting.
9 N-320420-0052-3     Wheeler Avenue Shared-Use Ped/Bike Path - (METRO)  Active  D           $0  No current issues
10 N-321037-0068-3     City Wide Overlay Design FY2014  Active  C,D,F,G,K  2  N/A  N/A  2015   $0  Work in progress for design Work Order No. 3.
11 N-321037-0074-3     City Wide Overlay / Rehabilitation FY17  Active  D           $0  Review in progress for Work Order No. 1.
12 N-321038-0010-3     Concrete Panel Replacement FY 2015  Active  B,D,E,I  2  N/A  N/A     $0  Awaiting proposal for Work Order No. 4
13 N-321040-075B-3     Pedestrian Bridge Replacements over HCFCD Channels  Active  C,D,E,K    April 10, 2025 (Actual)  January 27, 2027 (Expected)     $2,442,515  [08/31/2026] (a) Current Status/Milestones: EOR re-submitted the 100% Geotechnical Report with responses to HCFCD comments on 04/20/2026. HCFCD approval was received on 07/09/2026. EOR submitted 100% design for City review on 7/24/2026 for review(b) Issues/Modifications: None. (c) Mitigations/Action Items: Coordinate with EOR on 100% design submittal and continue progressing final design review. City 100% Review comments all received on 08/10/2026, EOR to address final comments. HCFCD is requesting copy of Maintenance agreement for approval which was provided on 8/28/2026. Project advertisement anticipated for 11/06/2026. (d) Assistance: N/A.
14 N-321040-A135-3     HSIP Safety Improvement Package No.1  Active  C,D,H,I    March 28, 2025 (Actual)  February 24, 2027 (Expected)     $461,452  09/04/2026 (a) Current Milestone: The bid tabulation & award recommendation concurrence memo is sent to SPD department for processing the SAP. Anticipated construction will start February 2027. (b) Issue: NSTR (c) Mitigations: NSTR (d) Assistance: No assistance is needed at this time.
15 R-000020-0032-3     Program Manager / Staff Augmentation for Wastewater Facilities - LS R/R  Active  D,E,I    May 11, 2015 (Actual)  N/A     $0  No current issues
16 R-000020-0089-3     Professional Services and Technical Support for Wastewater Operations Projects  Active  A,B,C,D,E,F,G,H,I,J,K,T           $0  No current issues
17 R-000020-0096-3     Work Order Professional Services, Technical Support, and Staff Augmentation Project  Active  A,B,C,D,E,F,G,H,I,J,K,T           $0  No current issues
18 R-000035-0015-3     Wastewater Force Main Renewal/Replacement For Highland Meadow and Bay Area Lift Stations  Active  D,E    August 23, 2019 (Actual)  August 14, 2024 (Delayed)  2024   $5,370,000  No current issues
19 R-000035-0029-3     Force Main Rehabilitation and Reconstruction Projects - Consent Decree (Goodyear Lift Station, Scarsdale Lift Station)  Active  D,E    August 27, 2024 (Actual)  September 01, 2027 (Expected)  2028   $6,653,000  No current issues
20 R-000265-0160-3     Chocolate Bayou Wastewater Treatment Plant improvements  Active  D    June 26, 2024 (Actual)  August 28, 2030 (Expected)  2027   $27,504,546  No current issues
21 R-000267-0179-3     Lift Station Rehabilitation and Reconstruction Design (Lockwood Lift Station, South Point Lift Station, Scott #3 Lift Station, Market St. #2 Lift Station, M.U.D. #067 Lift Station, Woodforest Lift Station) - Consent Decree  Active  D,E,H,I    July 30, 2024 (Actual)  August 25, 2027 (Expected)     $30,000,000  No current issues
22 R-000267-0183-3     Lift Station Hazard Mitigation and Improvement Projects FEMA - CD (Bayou Timber LS, 5th Street LS, Willowick LS, Heights LS, Bayou Place LS, North Macgregor Way #4 LS)  Active  C,D,G,I    July 02, 2025 (Actual)  January 19, 2028 (Expected)  2028   $23,700,000  No current issues
23 R-000267-0187-3     Lift Station Improvement Projects (Consent Decree) (Asbury LS, Ambrose LS, Studemont LS, Ardmore LS, Cottage Grove LS, & Stellalink LS)  Active  C,D,H,K    May 13, 2025 (Actual)  December 15, 2027 (Expected)  2028   $24,937,273  No current issues
24 R-000267-127A-3     LS Rehab Package 2: Scott #1  Active  D    July 07, 2014 (Actual)  August 30, 2028 (Expected)  2022   $24,433,882  No current issues
25 R-000298-0016-3     Almeda Sims WWTP Rehabilitation and Improvements  Pending  D        30   $0  No current issues
26 R-000298-004A-3      Almeda Sims Wastewater Treatment Plant Sludge Tanks 110 and 120 Repair.  Active  D           $0  No current issues
27 R-000536-0033-3     Force Main from Sagemont Lift Station to Southeast WWTP for the flow diversion  Active  D    October 25, 2019 (Actual)  September 20, 2023 (Actual)  2023   $20,163,821  No current issues
28 R-000536-0034-3     Flow diversion from Easthaven to Southeast WWTP - Package 1 Southeast WWTP to Fuqua & Blackhawk  Active  D    October 18, 2019 (Actual)  September 25, 2024 (Actual)  2024   $22,965,300  No current issues
29 R-002011-0106-3     Work Order Neighborhood Sewer Systems Improvement Projects (Consent Decree)  Active  A,B,C,D,E,F,G,H,I,J,K,T           $0  No current issues
30 R-002015-016A-3     Wastewater System/Substitute Service Support - Crestmont  Active  D    January 29, 2016 (Actual)  N/A  2021   $500,000  [7/3/20] (a) Milestone: Project has been transferred to WWOps. WWOps requesting CIPMS access. (b) Issues: NSTR (c) Mitigations: NSTR (d) Assistance: No assistance needed at this time.
31 S-000020-0071-3     Work Order Professional Engineering Services for Design of Large Diameter Waterline Technical Services - Package 1 (8500)  Active  A,B,C,D,E,F,G,H,I,K  253         $0  No current issues
32 S-000020-0093-3     Technical Services and Staff Augmentation for Neighborhood Water Line Replacement.  Active  A,C,D,E,F,G,H,I,J,K,T           $0  [8/20/26] ATP for Professional Engineering Services issued 8/25/2025- valid until 8/31/26. Trilogy Staff successfully onboarded and working on waterline projects. Authorization for contract extension up to 8/31/27 is out for signature.
33 S-000020-0094-3     On-Call Engineering Services for Drinking Water Operations Facilities City Wide Package 1  Active  A,B,C,D,E,F,G,H,I,J,K,T  2         $0  No current issues
34 S-000035-0298-3     Waterline Replacement in Midtown Area  Active  C,D    July 26, 2023 (Actual)  October 22, 2026 (Expected)     $5,775,000  [06/15/2026] Pre-Bid Conference date TBD (On Hold with SPD). Project selected for TWDB funding. Construction Contract is anticipated to be awarded in October, 2026.
35 S-000035-0303-3     WLR in Texas Medical Center (TMC) Area  Active  C,D,K    April 04, 2025 (Actual)  August 16, 2028 (Expected)  2030   $27,290,117  [5/15/26] Phase II has been initiated, including geotechnical investigation and survey efforts. The next milestone will be the 60% design submittal, anticipated in April 2027. Construction is currently anticipated to begin in FY2030. Due to the complexity of the project and the amount of easement acquisition required, the final project schedule will be further evaluated once the waterline alignment has been established and design efforts have progressed. The EOR will advise if adjustments to the overall project schedule are necessary.
36 S-000035-0308-3     WLR in UH Neighborhood  Active  D    September 22, 2025 (Actual)  February 10, 2028 (Expected)     $8,404,856  [08/11/26] The Phase I is completed. The RDAI signatures are completed. The Phase II design authorization is anticipated in August 2026, pending no unresolved issues. The estimated construction start is FY29.
37 S-000035-0314-3     WLR in Sunnyside Area  Active  D    May 28, 2025 (Delayed)  October 08, 2027 (Expected)  2028   $14,864,055  [9/11/26] (a) Current Milestone: 70% Submittals. 70% plan reviewed returned to EOR. 90% plan dues in 10/2026. has been routing for review. (b) Issue: None (c) Mitigations: None (d) Assistance: None
38 S-000035-0332-3     WLR in Sunnyside Area II  Active  D    November 18, 2025 (Actual)  April 27, 2028 (Expected)     $7,500,000  [9/11/25] (a) Current Milestone: Phase II 70% submittals. NTP for phase II was on Sept 11, 26. (b) Issue: None (c) Mitigations: None (d) Assistance: None
39 S-000701-0049-3     Large Diameter Water Line and Above Grade Crossings - Package 3  Active  A,B,D,E,G,H,I    November 03, 2025 (Actual)  November 08, 2028 (Expected)     $0  No current issues
40 S-000701-0050-3     Large Diameter Water Line and Valves Replacement - Package 4  Active  B,C,D,E,H,I,T    July 14, 2025 (Actual)  June 21, 2028 (Expected)     $0  No current issues
41 S-000900-0139-3     24-inch Water Line from Sunbeam Street to E Orem Drive along Martin Luther King Jr. Boulevard  Active  D      June 21, 2027 (Expected)  2027   $15,218,578  PDS states that this line should be built after the 4 Fuqua expansion projects starting with S-900-137 that goes to SH288.
42 S-000900-0186-3     48-inch Water Line from Forbes Road to Martindale Road along Almeda Genoa  Active  D    N/A  May 21, 2027 (Expected)  2027   $19,696,500  No current issues
43 S-000900-0310-3     42-inch Fuqua Line Extension from SH 288 to Hiram Clarke Rd  Active  D,K    June 25, 2025 (Actual)  December 13, 2028 (Expected)  2029   $44,090,909  No current issues
44 S-001000-0039-3     Building Improvements for Water Facilities at EWPP, NEWPP and Ardmore  Active  D,E,I    July 23, 2013 (Actual)  N/A     $0  No current issues