Construction Bench Mark 18m Report
 Engineering  Construction

Construction Bench Mark 18 Months Report: Projects in Design
Report Date: 10-31-2026

Benchmark Baseline data for Forecasted Critical Dates
Date Name Default Days Comments
N M R S
Date of Award 0 0 0 0 Engineering CR date #40
Forecast NTP 70 70 70 70
Forecast Subcomp 400 400 270 270 Use Construction days if available
Forecast Final Comp 45 45 45 45
Forecast Accept Work 70 70 70 70

No. WBS No Project Name Key Map Contract Amount Date of Award Forecast NTP Construction Days Substantial Comp Date Forecast Final Comp Forecast Accept Work
Managing Engineer Project Manager Contractor CM and I Senior Inspector Inspector
1  N-100043-0001-3   Bissonnet Corridor Safe Streets Project      $0.00   10-25-2028(s)   01-03-2029(s)      02-07-2030(s)   03-24-2030(s)   06-02-2030(s)                   
2  R-000265-0165-3   Kingwood Central Wastewater Treatment Plant WWTP Improvements -FEMA/CD   337F   $255,000,000.00   10-25-2028(s)   01-03-2029(s)      09-30-2029(s)   11-14-2029(s)   01-23-2030(s)                   
3  S-000900-0183-3   66-inch Water Line along Wheatley St, from Channel No. P118-32-01 to Victory Dr   412P,412T   $26,294,000.00   10-25-2028(s)   01-03-2029(s)      09-30-2029(s)   11-14-2029(s)   01-23-2030(s)   Panduranga Kuruva                
4  R-000267-0178-3   Lift Station Rehabilitation and Reconstruction Design(Heather Ridge Lift Station, M.C.M.U.D. #58 Lift Station, Will Clayton Lift Station, Trailwood Lift Station, Shady Maples Lift Station, Lake Village Lift Station, Brookdale Lift Station)   375J,296W,375A,336C,297N,336B,297S   $8,636,364.00   10-27-2027(s)   01-05-2028(s)   720   12-25-2029(s)   02-08-2030(s)   04-19-2030(s)                   
5  R-000267-0180-3   Lift Station Rehabilitation and Reconstruction Design FEMA - CD (Woodland Ridge LS, Ben's Branch LS, Elmwood Hills LS, Trail River LS, Forest Shores LS, Riverlawn LS)      $23,662,227.00   10-27-2027(s)   01-05-2028(s)   720   12-25-2029(s)   02-08-2030(s)   04-19-2030(s)                   
6  S-001000-053A-3   Facilities Improvements at Various Well Sites and Re-Pump Stations - Package 3A   409N,408R,408Q,408P,408N,409P,408R,529K,487Z   $12,928,600.00   10-27-2027(s)   01-05-2028(s)      10-01-2028(s)   11-15-2028(s)   01-24-2029(s)                   
7  S-000035-0284-3   Waterline Replacement in Independence Heights    453N,453J,452R,452M,453M,453K   $7,226,000.00   10-28-2026(s)   01-06-2027(s)   505   05-25-2028(s)   07-09-2028(s)   09-17-2028(s)                   
8  S-000900-0316-3   42-inch Water Line Sims Bayou Extension along US59   530E,530J,530N,530P,530S   $0.00   10-29-2031(s)   01-07-2032(s)      10-03-2032(s)   11-17-2032(s)   01-26-2033(s)                   
9  N-100042-0002-3   Telephone Road: Main Street Revitalization Project (Subproject 2)   534C,534G,534H,534M   $18,768,600.00   11-01-2028(s)   01-10-2029(s)      02-14-2030(s)   03-31-2030(s)   06-09-2030(s)   Yusherry Cang                
10  S-000035-0268-3   Watermain Replacement in Near Town-Montrose Area and Plainview Subdivision   492Q,492R,492U,492V   $12,315,089.00   11-04-2026(s)   01-13-2027(s)      10-10-2027(s)   11-24-2027(s)   02-02-2028(s)   Mohammad Sabzevari                
11  S-000701-0049-3   Large Diameter Water Line and Above Grade Crossings - Package 3    414S,415A,454D,454V,488D,488M,495N,496Y,533E,533F,536C   $0.00   11-08-2028(s)   01-17-2029(s)      10-14-2029(s)   11-28-2029(s)   02-06-2030(s)                   
12  S-000901-0017-3   Condition Assessment of 48-in WL along Galveston Rd and Allen Genoa Rd from Fuqua St to Steelman St      $10,000,000.00   11-08-2028(s)   01-17-2029(s)   651   10-30-2030(s)   12-14-2030(s)   02-22-2031(s)                   
13  N-100010-0001-3   Dunlavy Paving: West Dallas to Peden   492M,492R   $5,769,000.00   11-10-2027(s)   01-19-2028(s)      02-22-2029(s)   04-08-2029(s)   06-17-2029(s)   Sudarshan Gouni                
14  S-000035-0281-3   Waterline in Dissen Heights - Eastlawn Area   494T,494X,494Y   $11,545,000.00   11-11-2026(s)   01-20-2027(s)   500   06-03-2028(s)   07-18-2028(s)   09-26-2028(s)   Mohammad Sabzevari                
15  R-002011-0096-3   Gravity Sewer Line Adjustment   617C,617D,617G   $4,180,000.00   11-11-2027(s)   01-20-2028(s)   234   09-10-2028(s)   10-25-2028(s)   01-03-2029(s)                   
16  M-410043-0001-3   C106-10 Channel Improvement   576F   $41,359,500.00   11-15-2028(s)   01-24-2029(s)      02-28-2030(s)   04-14-2030(s)   06-23-2030(s)   Prakash Luetel                
17  S-000900-0136-3   72-inch Water Line along Greenbriar Dr to Metro Corridor to SWPS    491Z,492U,492W,492X,492Y   $78,660,700.00   11-15-2028(s)   01-24-2029(s)   651   11-06-2030(s)   12-21-2030(s)   03-01-2031(s)   Panduranga Kuruva                
18  S-000701-0038-3   Large Diameter Water Line and Valve Replacement Pkg. 3   495Z,496W,496X,496Y,536A   $14,064,000.00   11-17-2027(s)   01-26-2028(s)      10-22-2028(s)   12-06-2028(s)   02-14-2029(s)   Panduranga Kuruva                
19  N-MD0370-0007-3   N. Houston Rosslyn Road Sidewalk Improvements      $0.00   11-18-2026(s)   01-27-2027(s)      03-02-2028(s)   04-16-2028(s)   06-25-2028(s)                   
20  R-000265-0096-3   Upper Brays Wastewater Treatment Plant Improvements   529A   $13,884,000.00   11-18-2026(s)   01-27-2027(s)   450   04-21-2028(s)   06-05-2028(s)   08-14-2028(s)                   
21  S-000035-0283-3   Waterline Replacement in Near Northside   453Z,453V   $15,439,000.00   11-19-2025(p)   01-28-2026(p)      10-25-2026(p)   12-09-2026(p)   02-17-2027(p)                   
22  S-000200-029B-3   Ground Water Well Rehabilitation at Various Location - Package II      $0.00   11-24-2027(s)   02-02-2028(s)   500   06-16-2029(s)   07-31-2029(s)   10-09-2029(s)                   
23  N-210006-0001-3   Huntington Village Sec 4 Area Paving and Drainage   528U,528V,528Y,528Z   $15,999,000.50   11-30-2027(s)   02-08-2028(s)   1095   02-07-2031(s)   03-24-2031(s)   06-02-2031(s)   Prakash Luetel                
24  M-420HUD-006A-3   DR15 6A Edgewood Park Detention Basin    534X   $3,500,000.00   12-02-2026(s)   02-10-2027(s)      03-16-2028(s)   04-30-2028(s)   07-09-2028(s)   Prakash Luetel                
25  N-100008-0001-3   Fondren Road Paving and Drainage: Braeswood to Creekbend   530V,530Z   $15,780,407.00   12-06-2028(s)   02-14-2029(s)      03-21-2030(s)   05-05-2030(s)   07-14-2030(s)                   
26  N-100021-0001-3   Fondren Paving and Drainage from Creekbend to W. Airport   530Y,530Z,570C,570D,570G,570H   $25,719,952.00   12-06-2028(s)   02-14-2029(s)      03-21-2030(s)   05-05-2030(s)   07-14-2030(s)                   
27  R-000035-0028-3   Force Main Rehabilitation and Reconstruction Design Consent Decree - Songwood and Gessner#1 Lift Stations   496F,490J,490N   $3,889,346.00   12-08-2026(s)   02-16-2027(s)   340   01-22-2028(s)   03-07-2028(s)   05-16-2028(s)                   
28  M-420126-0142-3   River Hollow Lane Outfall Improvements    491R,491M   $1,137,112.24   12-08-2027(s)   02-16-2028(s)      03-22-2029(s)   05-06-2029(s)   07-15-2029(s)                   
29  R-000035-0031-3   Force Main Rehabilitation and Replacement for Gilpin, Reveille, and Berkely Lift Stations   535S,535K,576G   $0.00   12-08-2027(s)   02-16-2028(s)      11-12-2028(s)   12-27-2028(s)   03-07-2029(s)   Mohammad Haider                
30  S-000900-0310-3   42-inch Fuqua Line Extension from SH 288 to Hiram Clarke Rd   571M,572J,572K,572L,572M,573J   $44,090,909.09   12-13-2028(s)   02-21-2029(s)      11-18-2029(s)   01-02-2030(s)   03-13-2030(s)   Panduranga Kuruva                
31  S-000900-0184-3   66-inch Water Line along Victory Drive from Wheatley Street to Acres Homes Pump Station   412S,412T   $27,400,000.00   12-14-2028(s)   02-22-2029(s)      11-19-2029(s)   01-03-2030(s)   03-14-2030(s)   Panduranga Kuruva                
32  M-000126-0073-3   FY12 LDP Design Work Orders         12-15-2026(s)   02-23-2027(s)   730   02-22-2029(s)   04-08-2029(s)   06-17-2029(s)   Prakash Luetel                
33  R-000265-0158-3   White Oaks Wastewater Treatment Plant Improvements   411N   $17,948,717.94   12-15-2027(s)   02-23-2028(s)   720   02-12-2030(s)   03-29-2030(s)   06-07-2030(s)                   
34  R-000267-0187-3   Lift Station Improvement Projects (Consent Decree) (Asbury LS, Ambrose LS, Studemont LS, Ardmore LS, Cottage Grove LS, & Stellalink LS)      $24,937,272.73   12-15-2027(s)   02-23-2028(s)      11-19-2028(s)   01-03-2029(s)   03-14-2029(s)                   
35  R-002011-091C-3   Neighborhood Sewer Systems Improvements, Package 6 Area 3   490R   $2,000,000.00   12-15-2027(s)   02-23-2028(s)      11-19-2028(s)   01-03-2029(s)   03-14-2029(s)   Sudarshan Gouni                
36  N-100017-0001-3   Gessner Street Paving and Drainage Buffalo Bayou to Richmond   490W   $30,549,100.00   12-20-2028(s)   02-28-2029(s)      04-04-2030(s)   05-19-2030(s)   07-28-2030(s)                   
37  N-900001-0001-3   New TDO Buildings at Various Locations: 8002 Airline Drive and 5216 North McCarty Street    413T,455U,455V   $0.00   12-22-2027(s)   03-01-2028(s)      04-05-2029(s)   05-20-2029(s)   07-29-2029(s)                   
38  N-T20000-0012-3   Harwin Drive and Hillcroft Avenue Intersection Reconstruction   530D   $0.00   12-23-2026(s)   03-03-2027(s)      04-06-2028(s)   05-21-2028(s)   07-30-2028(s)                   
39  S-000035-0267-3   Water Line Rehabilitation in Central Park and Magnolia Park Subdivisions I   494U,494V,494Z,495S,495W   $0.00   12-27-2028(s)   03-07-2029(s)      12-02-2029(s)   01-16-2030(s)   03-27-2030(s)                   
40  R-000267-0182-3   Lift Station Hazard Mitigation and Improvement Projects FEMA - CD (Old Stone Trail LS, Tanya Circle LS, M.U.D. #175-2 LS, Memorial Dr #5 LS, Fleetwood LS, Addicks LS, Woodway #2 LS)   490R,488B,488E,488F   $32,333,333.33   12-29-2027(s)   03-08-2028(s)      12-03-2028(s)   01-17-2029(s)   03-28-2029(s)                   
41  M-420126-0152-3   Market Street - Storm Sewer Improvements   496K,496M   $4,141,000.00   12-30-2026(s)   03-10-2027(s)   180   09-06-2027(s)   10-21-2027(s)   12-30-2027(s)                   
42  S-000900-0149-3   54-inch Water Line along Genoa Red Bluff and Easements from SEWPP to Grayson St (aka SETL Contract G)   577L,577M,577P,577Q,577R   $17,000,000.00   01-03-2029(s)   03-14-2029(s)   365   03-14-2030(s)   04-28-2030(s)   07-07-2030(s)   Panduranga Kuruva                
43  M-410040-0001-3   Braeburn Glen Area Drainage and Paving Improvements   530P,530S,530T,530N   $21,578,033.70   01-06-2027(s)   03-17-2027(s)      04-20-2028(s)   06-04-2028(s)   08-13-2028(s)   Prakash Luetel                
44  M-410039-0002-3   Drainage and Paving Improvements for Cottage Grove East, Phase II   492C,492G   $24,339,658.06   01-08-2027(s)   03-19-2027(s)      04-22-2028(s)   06-06-2028(s)   08-15-2028(s)                   
45  R-000265-0167-3   Wastewater Treatment Plant Hazard Mitigation _Forest Cove WWTP (FN 565) FEMA - CD   336E   $25,128,205.00   01-10-2029(s)   03-21-2029(s)      12-16-2029(s)   01-30-2030(s)   04-10-2030(s)                   
46  S-001000-056D-3   LAS System at Ground Water Facilities and Chemical Improvements at Repump Stations - Package 5   528R,529P,528V,529S,529L,529W,488U   $7,169,100.00   01-10-2029(s)   03-21-2029(s)   570   10-12-2030(s)   11-26-2030(s)   02-04-2031(s)                   
47  R-000536-0035-3   Wrightwood SSO elimination   493C   $2,779,000.00   01-12-2028(s)   03-22-2028(s)      12-17-2028(s)   01-31-2029(s)   04-11-2029(s)                   
48  S-000035-0300-3   WLR in Interstate 10 and Market Street Subdivisions   496L,496M,496K,496F   $6,001,361.00   01-13-2028(s)   03-23-2028(s)      12-18-2028(s)   02-01-2029(s)   04-12-2029(s)                   
49  S-000600-0057-3   Rehabilitation of Water Storage Tanks - Package 17   530W,571P,572J,617B,369H,496U   $0.00   01-13-2028(s)   03-23-2028(s)      12-18-2028(s)   02-01-2029(s)   04-12-2029(s)   Tina Yao                
50  S-000035-0316-3   WMR in Spring Branch East, District 73 along Halifax, EBS, Court, Hiram, and South Areas    338Y,338Z,378D,451X,451Y,451Z,491C,492A,493R,494N,494P,494S,496D,496H,497A,611C,611D,611H   $18,540,784.50   01-17-2028(s)   03-27-2028(s)      12-22-2028(s)   02-05-2029(s)   04-16-2029(s)                   
51  R-002011-091B-3   Neighborhood Sewer System Improvements, Package 6 Area 2   489C   $7,050,000.00   01-17-2029(s)   03-28-2029(s)      12-23-2029(s)   02-06-2030(s)   04-17-2030(s)   Sudarshan Gouni                
52  N-000386-001A-3   Tanglewood Area Street Rehab (NSR 454 B)   491K,491L,491P,491Q   $9,201,405.00   01-19-2028(s)   03-29-2028(s)      05-03-2029(s)   06-17-2029(s)   08-26-2029(s)   Sam Habibi                
53  S-000900-0146-3   36-inch Water Line along Medical Center Blvd, Channel A111-00-00 and Bay Area Blvd from Galveston Rd to Beamer Rd (aka SETL Contract D)   617Z,618T,618W,618X   $18,217,200.00   01-19-2028(s)   03-29-2028(s)   550   09-30-2029(s)   11-14-2029(s)   01-23-2030(s)   Panduranga Kuruva                
54  R-001000-0038-3   CRMP CIP Package 2 (CD Area 2 and 3)   494L,494Q   $281,843,700.00   01-23-2029(s)   04-03-2029(s)      12-29-2029(s)   02-12-2030(s)   04-23-2030(s)                   
55  R-000265-0161-3   Northbelt Wastewater Treatment Plant Improvements and Expansion   454Y   $71,525,000.00   01-26-2028(s)   04-05-2028(s)   720   03-26-2030(s)   05-10-2030(s)   07-19-2030(s)                   
56  R-000265-0163-3   Cedar Bayou Wastewater Treatment Plant improvements and Expansion - FEMA   298Y,298Z,378C   $144,000,000.00   01-26-2028(s)   04-05-2028(s)      12-31-2028(s)   02-14-2029(s)   04-25-2029(s)                   
57  R-000265-0113-3   Clinton Park Wastewater Treatment Plant (WWTP) Improvements   495Y   $9,870,000.00   01-27-2027(s)   04-07-2027(s)   450   06-30-2028(s)   08-14-2028(s)   10-23-2028(s)                   
58  N-310662-0049-3   Citywide Intersection Safety Improvements (FY 16)   000A   $0.00   01-30-2019(s)   04-10-2019(s)      05-14-2020(s)   06-28-2020(s)   09-06-2020(s)                   
59  S-000035-0307-3   WLR in Shadowbriar and Southlake Areas   488V,489S   $14,833,962.00   02-02-2028(s)   04-12-2028(s)      01-07-2029(s)   02-21-2029(s)   05-02-2029(s)                   
60  R-001000-0034-3   CRMP Package 9 - Areas 8 and 11 - Basins IB032 and IB022   495E,494A,495H   $27,577,880.00   02-08-2028(s)   04-18-2028(s)   746   05-04-2030(s)   06-18-2030(s)   08-27-2030(s)                   
61  N-100024-0001-3   Hirsch: Laura Koppe to Crosstimbers Paving and Drainage Improvements   454F,454K   $17,408,000.00   02-07-2029(s)   04-18-2029(s)      05-23-2030(s)   07-07-2030(s)   09-15-2030(s)   Mohammad Sabzevari                
62  S-000035-0308-3   WLR in UH Neighborhood   493Z,533C,533D,533G,533H,534A,534E   $8,404,856.00   02-10-2028(s)   04-20-2028(s)      01-15-2029(s)   03-01-2029(s)   05-10-2029(s)                   
63  N-MD0180-0001-3   Airline Dr Intersection Improvements (HSIP-26)      $0.00   02-10-2027(s)   04-21-2027(s)      05-25-2028(s)   07-09-2028(s)   09-17-2028(s)                   
64  N-T08000-0008-3   Hartman Middle School & Alcott Elementary School Safe Routes to School (SRTS) Project      $0.00   02-10-2027(s)   04-21-2027(s)      05-25-2028(s)   07-09-2028(s)   09-17-2028(s)                   
65  N-310650-0086-3   Citywide Traffic Signal Rebuild Package #12 (FY17)   411A      02-13-2019(s)   04-24-2019(s)   730   04-23-2021(s)   06-07-2021(s)   08-16-2021(s)                   
66  M-410291-0001-3   Turkey Gully Drainage and Paving   452T,452U   $15,036,211.58   02-17-2027(s)   04-28-2027(s)   400   06-01-2028(s)   07-16-2028(s)   09-24-2028(s)   Prakash Luetel                
67  R-001000-0033-3   CRMP Package 8 - Area 1- Basin IB043   454L,454Q,454U   $83,854,000.00   02-19-2028(s)   04-29-2028(s)      01-24-2029(s)   03-10-2029(s)   05-19-2029(s)                   
68  S-000035-0299-3   WLR in Greater Eastwood & Second Ward   493R,494N,494P,493V,494S   $18,068,012.50   02-23-2028(s)   05-03-2028(s)      01-28-2029(s)   03-14-2029(s)   05-23-2029(s)                   
69  N-321040-A135-3   HSIP Safety Improvement Package No.1   492X,576J,533Z,493M,575M   $461,452.40   02-24-2027(s)   05-05-2027(s)      06-08-2028(s)   07-23-2028(s)   10-01-2028(s)                   
70  N-321040-B135-3   HSIP Safety Improvement Package No.2   570G,570H,570L,570M,570Q,570R,531B,531F,531K,528H,528M,528R   $2,078,511.06   02-24-2027(s)   05-05-2027(s)      06-08-2028(s)   07-23-2028(s)   10-01-2028(s)                   
71  R-001000-0032-3   CRMP Package 7- Area 1- Basin IB043   454C,454G,454L   $81,966,435.00   02-28-2028(s)   05-08-2028(s)      02-02-2029(s)   03-19-2029(s)   05-28-2029(s)                   
72  S-000035-0302-3   WLR in Houston Heights (South)   492D,452Z,452V   $11,770,370.50   03-06-2028(s)   05-15-2028(s)      02-09-2029(s)   03-26-2029(s)   06-04-2029(s)                   
73  S-000035-0313-3   WLR in Oak Forest-Area A      $6,590,876.00   03-07-2028(s)   05-16-2028(s)      02-10-2029(s)   03-27-2029(s)   06-05-2029(s)                   
74  M-410028-0001-3   Westbury Area Drainage and Paving Improvements Subproject 1   571A,571B,571E,571F   $25,703,050.00   03-10-2027(s)   05-19-2027(s)      06-22-2028(s)   08-06-2028(s)   10-15-2028(s)                   
75  R-001000-0031-3   CRMP Package 6- Area 1- Basin IB043   414X,454B,454C   $88,301,600.00   03-14-2028(s)   05-23-2028(s)      02-17-2029(s)   04-03-2029(s)   06-12-2029(s)                   
76  S-000056-0084-3   East Water Purification Plant (EWPP) Mechanical and Electrical Improvements for Plant 1 and 2 - Package 2   496U,496Y   $57,589,840.00   03-15-2028(s)   05-24-2028(s)      02-18-2029(s)   04-04-2029(s)   06-13-2029(s)                   
77  S-001000-053B-3   of Facilities Improvements at Various Well Sites and Re-Pump Stations - Package 4   449T,449U,449L,449G,448Y,449X,449Q,528H,528K,528M,528C,489U   $6,029,300.00   03-15-2028(s)   05-24-2028(s)      02-18-2029(s)   04-04-2029(s)   06-13-2029(s)                   
78  R-001000-0040-3   CRMP CIP Package 10 (Area1 - Basin IB043)   414W   $58,652,078.63   03-18-2028(s)   05-27-2028(s)   730   05-27-2030(s)   07-11-2030(s)   09-19-2030(s)                   
79  R-000267-0186-3   Lift Station Hazard Mitigation and Improvement Projects FEMA - CD (Forest Cove Dr. #1 LS, Forest Cove Dr. #2 LS, Marina LS, Kingwood Dr. LS, Deer Ridge Estates LS, Forest Garden LS, Aqua Vista LS, River Lift Station)      $20,833,333.00   03-22-2028(s)   05-31-2028(s)      02-25-2029(s)   04-11-2029(s)   06-20-2029(s)                   
80  M-420HUD-013A-3   DR15 13A EP Hill Park Detention Basin   533V   $3,809,862.00   03-26-2027(s)   06-04-2027(s)      07-08-2028(s)   08-22-2028(s)   10-31-2028(s)   Prakash Luetel                
81  M-430296-0018-3   Boone Park and Hackberry Park Detention Basins   529K,528M   $15,400,000.00   03-26-2027(s)   06-04-2027(s)      07-08-2028(s)   08-22-2028(s)   10-31-2028(s)                   
82  S-000035-0317-3   WLR in Oak Forest-Area B   451M,451R,452J,452N   $8,400,978.00   03-27-2028(s)   06-05-2028(s)      03-02-2029(s)   04-16-2029(s)   06-25-2029(s)                   
83  N-321040-075B-3   Pedestrian Bridge Replacements over HCFCD Channels   532F,530Z,573C,337B   $2,442,515.00   03-31-2027(s)   06-09-2027(s)      07-13-2028(s)   08-27-2028(s)   11-05-2028(s)                   
84  R-000267-0174-3   Lift Station Rehabilitation and Reconstruction Design Consent Decree: Ladbrook, Pine Prairie, Stately Oaks, Chestnut Ridge and Magnolia Park   336B,297P,298W,336A,495S   $38,473,768.46   03-31-2027(s)   06-09-2027(s)   720   05-29-2029(s)   07-13-2029(s)   09-21-2029(s)                   
85  S-000900-0147-3   24-Inch Water Line along Highway 3 from Fuqua Street to Dixie Farm Road (FM1959) (aka SETL Contract E)   576R,577N,577S,577X   $12,857,330.31   03-31-2027(s)   06-09-2027(s)   683   04-22-2029(s)   06-06-2029(s)   08-15-2029(s)   Panduranga Kuruva                
86  S-000066-A011-3   Work order #1 for project advisor/technical consultant services for Northeast Water Purification Plant Expansion.   377W   $0.00   04-03-2013(s)   06-12-2013(s)   120   10-10-2013(s)   11-24-2013(s)   02-02-2014(s)                   
87  S-000066-B011-3   Work Order #2 - Study System Failure @ NEWPP After Feb-2012 Storm Event   377W   $0.00   04-03-2013(s)   06-12-2013(s)   120   10-10-2013(s)   11-24-2013(s)   02-02-2014(s)                   
88  S-000066-C011-3   Work Order #2A - Study System Failure @ NEWPP After Jun-2012 Storm Event   377W   $0.00   04-03-2013(s)   06-12-2013(s)   180   12-09-2013(s)   01-23-2014(s)   04-03-2014(s)                   
89  S-000066-D011-3   Work Order #3 - Authority Engagement for Project Advisor/Technical Consultant Services for Northeast Water Purification Plant (NEWPP) Expansion   377W   $0.00   04-03-2013(s)   06-12-2013(s)      03-09-2014(s)   04-23-2014(s)   07-02-2014(s)                   
90  M-410040-001A-3   Sharpstown Area Detention Pond A    530U   $9,258,857.21   04-07-2027(s)   06-16-2027(s)   434   08-23-2028(s)   10-07-2028(s)   12-16-2028(s)   Prakash Luetel                
91  M-42LHUD-0006-3   CDBG-MIT Frenchtown Drainage and Paving Improvements   494A,494B,454W,454X   $9,914,476.00   04-12-2028(s)   06-21-2028(s)   180   12-18-2028(s)   02-01-2029(s)   04-12-2029(s)   Prakash Luetel                
92  M-410035-001A-3   Northside High School Area - Sanitary Sewer Rehab   493C,493D   $9,098,672.00   04-14-2027(s)   06-23-2027(s)      07-27-2028(s)   09-10-2028(s)   11-19-2028(s)   Prakash Luetel                
93  S-000900-0309-3   Professional Engineering Services for the Technical Advisor Support for the Surface Water Transmission Program   114M   $0.00   04-24-2025(p)   07-03-2025(p)      03-30-2026(p)   05-14-2026(p)   07-23-2026(p)                   
94  S-000035-0305-3   WLR in Shady Acres   492C,452C,452P,452Q,452S,452T,452U,452Y   $13,124,810.00   04-25-2028(s)   07-04-2028(s)      03-31-2029(s)   05-15-2029(s)   07-24-2029(s)                   
95  M-410041-0001-3   Wheeler and MLK Detention Basins, RR Culvert, and KG Expansion   534J,534K,534G,534F   $20,570,000.00   04-25-2029(s)   07-04-2029(s)      08-08-2030(s)   09-22-2030(s)   12-01-2030(s)   Prakash Luetel                
96  M-410041-001A-3   Kuhlman Gully Detention Basin   534G,534F,534K   $0.00   04-25-2029(s)   07-04-2029(s)      08-08-2030(s)   09-22-2030(s)   12-01-2030(s)   Prakash Luetel                
97  N-210015-0001-3   Paving and Drainage Improvements in Alief Forest South Area- Sub-Project 1   529J,529N   $39,843,581.00   04-26-2028(s)   07-05-2028(s)   540   12-27-2029(s)   02-10-2030(s)   04-21-2030(s)   Sudarshan Gouni                
98  R-000267-0185-3   Lift Station Hazard Mitigation and Improvement Projects FEMA - CD (Sunnyglen Dr LS, Scotts Point LS, Woodstream LS, Riverchase Trail LS, Aspen Pass LS, Covecrest LS, and Spanish Cove LS)   338L,338L,297Q,297V,297R,338V,338Y   $11,375,000.00   04-27-2028(s)   07-06-2028(s)      04-02-2029(s)   05-17-2029(s)   07-26-2029(s)                   
99  N-210004-0001-3   Cloverland Area Paving and Drainage Improvements   573L,573M   $23,701,000.00   04-28-2027(s)   07-07-2027(s)      08-10-2028(s)   09-24-2028(s)   12-03-2028(s)   Sudarshan Gouni                
100  N-210008-0001-3   Gray and Taft Area Paving and Drainage   493N,493P   $8,186,187.00   04-28-2027(s)   07-07-2027(s)   180   01-03-2028(s)   02-17-2028(s)   04-27-2028(s)   Sudarshan Gouni                
101  R-000265-0151-3   Sims North Wastewater Treatment Plant Improvements - Package 3   535H   $12,953,100.00   04-28-2027(s)   07-07-2027(s)      04-02-2028(s)   05-17-2028(s)   07-26-2028(s)                   
102  R-002011-0091-3   Neighborhood Sewer Systems Improvements, Package 6   489C,490R,491Y,491X      04-30-2025(p)   07-09-2025(p)      04-05-2026(p)   05-20-2026(p)   07-29-2026(p)   Mohammad Sabzevari                
103  R-000267-0184-3   Lift Station Hazard Mitigation and Improvement Projects FEMA - CD (Mississippi LS, Berkley LS, Hunterwood M.U.D. LS, Ballantine LS, Minnesota LS, Kirby Drive #3 LS)      $26,875,000.00   05-04-2028(s)   07-13-2028(s)      04-09-2029(s)   05-24-2029(s)   08-02-2029(s)                   
104  R-002011-090C-3   Neighborhood Sewer Systems Improvements Deer Ridge Estates and Fondren Gardens   571J,336L   $2,359,000.00   05-06-2027(s)   07-15-2027(s)   305   05-15-2028(s)   06-29-2028(s)   09-07-2028(s)                   
105  S-000035-0311-3   WLR in Memorial Neighborhod-Area B   489B,489F   $10,272,393.20   05-08-2028(s)   07-17-2028(s)      04-13-2029(s)   05-28-2029(s)   08-06-2029(s)                   
106  S-000900-0315-3   30-inch Water Line along Bellaire Boulevard   529E,529F,529G,529H,530E   $0.00   05-08-2030(s)   07-17-2030(s)      04-13-2031(s)   05-28-2031(s)   08-06-2031(s)                   
107  N-100006-0001-3   University Blvd Paving & Drainage Kirby Drive to Greenbriar Drive   532H   $6,122,000.00   05-12-2027(s)   07-21-2027(s)      08-24-2028(s)   10-08-2028(s)   12-17-2028(s)                   
108  N-100042-0001-3   Telephone Road: Main Street Revitalization Project (Subproject 1)   494X,534B,534C   $5,343,300.00   05-12-2027(s)   07-21-2027(s)   1070   06-25-2030(s)   08-09-2030(s)   10-18-2030(s)   Yusherry Cang                
109  S-000035-0315-3   WLR in South Gessner Area    570D,570H,570M,571A,571H,571E   $7,223,555.00   05-15-2028(s)   07-24-2028(s)      04-20-2029(s)   06-04-2029(s)   08-13-2029(s)                   
110  S-000035-0270-3   Watermain Replacement in Second Ward Area   494N,494P,494S,494T   $13,561,527.00   05-19-2027(s)   07-28-2027(s)      04-23-2028(s)   06-07-2028(s)   08-16-2028(s)   Mohammad Sabzevari                
111  R-000267-0188-3   Lift Station Improvement Projects (Consent Decree) (North Houston-Rosslyn LS, Pinemont LS, Hollister LS, Windfern LS, Mitchell LS, & Northcourt LS)   411N,451H,450D,410X,412R,410Y   $18,605,025.00   05-19-2028(s)   07-28-2028(s)   610   03-30-2030(s)   05-14-2030(s)   07-23-2030(s)                   
112  S-000035-0288-3   Waterline Replacement in Fortbend Houston , Jensen Tidwell, Parkette And Homewood Denton Areas   571W,571S,570Z,570V   $15,635,970.00   05-21-2027(s)   07-30-2027(s)      04-25-2028(s)   06-09-2028(s)   08-18-2028(s)                   
113  S-000900-0186-3   48-inch Water Line from Forbes Road to Martindale Road along Almeda Genoa   575N,574R,574Q,574P   $19,696,500.00   05-21-2027(s)   07-30-2027(s)   551   01-31-2029(s)   03-17-2029(s)   05-26-2029(s)   Panduranga Kuruva                
114  M-410006-0002-3   Arlington Heights Area Drainage Improvements Sub Project 2   576C,576G   $14,723,234.00   05-26-2027(s)   08-04-2027(s)      09-07-2028(s)   10-22-2028(s)   12-31-2028(s)   Yusherry Cang                
115  S-000900-0180-3   24-Inch Water Line along West Road from Deer Trail Drive to North IH 45 (East ROW)   412C,412D   $7,521,149.20   05-29-2028(s)   08-07-2028(s)   310   06-13-2029(s)   07-28-2029(s)   10-06-2029(s)   Panduranga Kuruva                
116  N-000818-0001-3   Fulton Street Reconstruction from Quitman to Hogan Street   493H   $7,326,565.22   05-31-2027(s)   08-09-2027(s)   635   05-05-2029(s)   06-19-2029(s)   08-28-2029(s)                   
117  S-000900-0179-3   66-inch Water Line along Greens Crossing Blvd, Channel No. P118-30-01, from Tall Pine Valley Dr to Turney Dr   412C,412G   $24,700,000.00   05-31-2028(s)   08-09-2028(s)      05-06-2029(s)   06-20-2029(s)   08-29-2029(s)   Panduranga Kuruva                
118  S-000035-0332-3   WLR in Sunnyside Area II      $7,500,000.00   06-01-2028(s)   08-10-2028(s)      05-07-2029(s)   06-21-2029(s)   08-30-2029(s)                   
119  M-430296-0017-3   TIRZ17 Memorial City Area Detention Basin   489D,489H,490A   $71,885,436.69   06-02-2027(s)   08-11-2027(s)   730   08-10-2029(s)   09-24-2029(s)   12-03-2029(s)                   
120  R-000267-0183-3   Lift Station Hazard Mitigation and Improvement Projects FEMA - CD (Bayou Timber LS, 5th Street LS, Willowick LS, Heights LS, Bayou Place LS, North Macgregor Way #4 LS)   492D,493L,491G,493E,534E,492N   $23,700,000.00   06-07-2028(s)   08-16-2028(s)      05-13-2029(s)   06-27-2029(s)   09-05-2029(s)                   
121  S-000900-0144-3   54-inch Water Line along Galveston Road from HCFCD Channel No B104-05-00 to Clear Lake City Water Authority Pump Station No. 3 (aka SETL Contract B)   617H,617M,618J,618N,618T   $31,000,500.00   06-09-2027(s)   08-18-2027(s)   540   02-08-2029(s)   03-25-2029(s)   06-03-2029(s)   Panduranga Kuruva                
122  M-410016-001B-3   Westridge and Braes Terrace Area Drainage and Paving   532K,532N,532P,532Q,532T   $6,491,689.00   06-14-2028(s)   08-23-2028(s)      09-27-2029(s)   11-11-2029(s)   01-20-2030(s)   Sam Habibi                
123  R-000035-0032-3   Force Main Rehabilitation and Replacement for Trail River, Lake Village, and Bens Branch Lift Stations   337D,336N,337F   $0.00   06-14-2028(s)   08-23-2028(s)      05-20-2029(s)   07-04-2029(s)   09-12-2029(s)                   
124  S-000035-0304-3   WLR in Melrose Park Neighborhood Area   413Q,413U,413P,413T   $13,344,086.00   06-19-2028(s)   08-28-2028(s)      05-25-2029(s)   07-09-2029(s)   09-17-2029(s)                   
125  S-000900-0139-3   24-inch Water Line from Sunbeam Street to E Orem Drive along Martin Luther King Jr. Boulevard   573H,573M   $15,218,578.00   06-21-2027(s)   08-30-2027(s)   508   01-19-2029(s)   03-05-2029(s)   05-14-2029(s)   Panduranga Kuruva                
126  S-000701-0050-3   Large Diameter Water Line and Valves Replacement - Package 4    412S,412T,414U,455T,493K,493L,493Y,494N,494P,494X,496Q,496U,493J,536C   $0.00   06-21-2028(s)   08-30-2028(s)      05-27-2029(s)   07-11-2029(s)   09-19-2029(s)                   
127  M-410016-001A-3   Westridge and Braes Terrace Area Drainage and Paving Improvements Phase 1A    532N,532P   $9,177,000.00   06-23-2027(s)   09-01-2027(s)      10-05-2028(s)   11-19-2028(s)   01-28-2029(s)   Sam Habibi                
128  S-000900-0182-3   66-inch Water Line along Veteran Memorial Drive and West Gulf Bank Rd, from TX-249 to Ella Blvd   412K,412P   $9,636,000.00   06-23-2028(s)   09-01-2028(s)      05-29-2029(s)   07-13-2029(s)   09-21-2029(s)   Panduranga Kuruva                
129  M-410015-0002-3   Magnolia Park Sec. 2 Area Drainage and Paving Subproject 2   495S,495W,495X,535A,535B   $20,800,453.91   06-25-2025(s)   09-03-2025(s)   730   09-03-2027(s)   10-18-2027(s)   12-27-2027(s)   Prakash Luetel                
130  S-000900-0178-3   66-inch Water Line along Green Plaza Dr, Fallbrook Dr from Plaza Verde Dr to Greens Crossing Blvd (MUD #321)   372U,372Y,412C   $19,950,000.00   06-28-2028(s)   09-06-2028(s)   730   09-06-2030(s)   10-21-2030(s)   12-30-2030(s)   Panduranga Kuruva                
131  R-001000-0037-3   CRMP CIP Package 1 (CD Area 2 and 3)   494K,494L,494Q   $90,810,642.00   07-03-2029(s)   09-11-2029(s)      06-08-2030(s)   07-23-2030(s)   10-01-2030(s)                   
132  N-100036-0001-3   Chimney Rock Road Connectivity at Fort Bend Toll Road   571F,571K,571L   $3,900,000.00   07-06-2027(s)   09-14-2027(s)   253   05-24-2028(s)   07-08-2028(s)   09-16-2028(s)   Mohammad Sabzevari                
133  S-000035-0306-3   WLR in Ashford South and Ashford Village Areas      $9,604,011.99   07-06-2028(s)   09-14-2028(s)      06-11-2029(s)   07-26-2029(s)   10-04-2029(s)                   
134  M-410025-0001-3   Inwood Forest Area Drainage and Paving (SP1 and SP2)   411P,411Q,411T,411U   $29,231,345.85   07-07-2027(s)   09-15-2027(s)      10-19-2028(s)   12-03-2028(s)   02-11-2029(s)                   
135  N-100030-003C-3   Antoine Paving and Drainage: Cole Creek to Victory   411U,411Y,451C   $0.00   07-11-2029(s)   09-19-2029(s)      10-24-2030(s)   12-08-2030(s)   02-16-2031(s)                   
136  S-000100-0026-3   New/Replacement of Water Well IAH Well 4   374A   $8,561,563.00   07-22-2027(s)   09-30-2027(s)   500   02-11-2029(s)   03-28-2029(s)   06-06-2029(s)                   
137  R-000265-0154-3   Sims Bayou South Wastewater Treatment Plant Improvements Package 3   535L   $69,130,942.00   07-26-2028(s)   10-04-2028(s)   515   03-03-2030(s)   04-17-2030(s)   06-26-2030(s)   Singarpal Sekhon                
138  R-000265-0160-3   Chocolate Bayou Wastewater Treatment Plant improvements   574E   $27,504,546.00   07-26-2028(s)   10-04-2028(s)   872   02-23-2031(s)   04-09-2031(s)   06-18-2031(s)   Singarpal Sekhon                
139  R-000265-0168-3   Wastewater Treatment Plant Hazard Mitigation _ WCID 76 WWTP (FN 485) FEMA - CD    415E   $27,500,000.00   07-26-2028(s)   10-04-2028(s)      07-01-2029(s)   08-15-2029(s)   10-24-2029(s)                   
140  R-000267-0177-3   Lift Station Rehabilitation and Reconstruction Design FEMA - CD (Kingwood Place South LS, Golden Bear LS, Deer Springs LS, AG Farm LS, Golf Course LS)   335H,336A,336G,336H   $18,536,000.00   07-26-2028(s)   10-04-2028(s)   720   09-24-2030(s)   11-08-2030(s)   01-17-2031(s)                   
141  R-000267-0181-3   Lift Station Rehabilitation Electrical Improvements Consent Decree      $22,375,490.00   07-26-2028(s)   10-04-2028(s)   720   09-24-2030(s)   11-08-2030(s)   01-17-2031(s)                   
142  R-000267-127A-3   LS Rehab Package 2: Scott #1   493Z   $24,433,882.00   07-26-2028(s)   10-04-2028(s)      07-01-2029(s)   08-15-2029(s)   10-24-2029(s)                   
143  S-000900-0143-3   54-inch Water Line along BW8, Duffer Ln, Perimeter Rd and Highway 3 from Grayson St to HCFCD Channel No. B104-05-00 (aka SETL Contract A)   532U,532V,533S,533T,533U,533V   $30,500,000.00   07-26-2028(s)   10-04-2028(s)   980   06-11-2031(s)   07-26-2031(s)   10-04-2031(s)   Panduranga Kuruva                
144  R-000265-0159-3   Beltway Wastewater Treatment Plant Improvements   529G   $19,350,000.00   07-28-2027(s)   10-06-2027(s)   720   09-25-2029(s)   11-09-2029(s)   01-18-2030(s)                   
145  R-000265-0162-3   Greenridge Wastewater Treatment Plant improvements   571X   $25,551,273.00   07-28-2027(s)   10-06-2027(s)   364   10-04-2028(s)   11-18-2028(s)   01-27-2029(s)   Singarpal Sekhon                
146  R-000509-0041-3   69th Street Wastewater Treatment Plant Improvements( Package 7)   494R   $6,000,000.00   07-28-2027(s)   10-06-2027(s)      07-02-2028(s)   08-16-2028(s)   10-25-2028(s)                   
147  R-002011-0089-3   Neighborhood Sewer System Improvements (AS069)   492Q,492U,492V   $26,888,693.00   07-28-2027(s)   10-06-2027(s)   1020   07-22-2030(s)   09-05-2030(s)   11-14-2030(s)                   
148  N-000664-0002-3   Greens Road: John F. Kennedy Boulevard to US 59   374P,374Q,374R,375N   $46,930,108.00   07-30-2027(s)   10-08-2027(s)      11-11-2028(s)   12-26-2028(s)   03-06-2029(s)   Mohammad Sabzevari                
149  S-000701-0043-3   Miscellaneous Large Diameter Water Line Improvements - Package 4   490A,490B,493K,493L,493M   $17,513,250.00   08-04-2027(s)   10-13-2027(s)   545   04-10-2029(s)   05-25-2029(s)   08-03-2029(s)   Panduranga Kuruva                
150  S-000900-0305-3   Groundwater Reduction Plan (GRP) Conversion Waterlines NW Area Group B   372Q,372S,372T,372U,371V,372P,372V,371S,371T,371V   $2,121,000.00   08-09-2028(s)   10-18-2028(s)   375   10-28-2029(s)   12-12-2029(s)   02-20-2030(s)   Panduranga Kuruva                
151  S-000701-0041-3   Miscellaneous Large Diameter Waterline Improvements - Pkg 3    412S,412T,454N,455Y,491Y,491Z,532V,534D,535A,535F,535G,535K,535L,570H,571E,571J,576R   $14,719,440.00   08-11-2027(s)   10-20-2027(s)   2047   05-28-2033(s)   07-12-2033(s)   09-20-2033(s)   Panduranga Kuruva                
152  M-430241-011G-3   SWPS-FWS Work Order 7 [DESIGN]      $0.00   08-14-2019(s)   10-23-2019(s)      11-26-2020(s)   01-10-2021(s)   03-21-2021(s)                   
153  S-000900-0148-3   Highway 3 Distribution Water Line from Dixie Farm Road to north of West Texas Avenue (aka SETL Contract F)   577X,617B,617C,617G,617H,617M,617R,618N   $7,000,000.00   08-15-2029(s)   10-24-2029(s)   450   01-17-2031(s)   03-03-2031(s)   05-12-2031(s)   Panduranga Kuruva                
154  S-000035-0303-3   WLR in Texas Medical Center (TMC) Area   532D,532G,532H,532L,532M,532Q,532R,532V,533A,533E,533F,533J,533K,533N,533P,533S,533S,533T   $27,290,117.00   08-16-2028(s)   10-25-2028(s)      07-22-2029(s)   09-05-2029(s)   11-14-2029(s)                   
155  R-000267-178A-3   Lift Station Rehabilitation and Reconstruction Design (Trailwood Lift Station and Lake Village Lift Station)      $4,090,910.00   08-18-2027(s)   10-27-2027(s)   495   03-05-2029(s)   04-19-2029(s)   06-28-2029(s)   Singarpal Sekhon                
156  R-001000-0036-3   CRMP CIP Package 5 - Sanitary Sewer Improvements Upstream of Eddington LS    534C,494Y,494X   $17,397,304.40   08-20-2027(s)   10-29-2027(s)      07-25-2028(s)   09-08-2028(s)   11-17-2028(s)                   
157  S-000900-0181-3   66-inch Water Line along Veterans Memorial Drive    412C,412F,412K   $8,482,650.00   08-23-2028(s)   11-01-2028(s)   448   01-23-2030(s)   03-09-2030(s)   05-18-2030(s)   Panduranga Kuruva                
158  R-000265-0146-3   Sims South Wastewater Treatment Plant Improvement   535L   $24,682,000.00   08-25-2027(s)   11-03-2027(s)   730   11-02-2029(s)   12-17-2029(s)   02-25-2030(s)                   
159  R-000265-0150-3   Northwest Wastewater Treatment Plant Improvements   451C   $46,850,845.00   08-25-2027(s)   11-03-2027(s)   915   05-06-2030(s)   06-20-2030(s)   08-29-2030(s)   Singarpal Sekhon                
160  R-000267-0176-3   Lift Station Rehabilitation and Reconstruction Projects(Carvel Lane Lift Station, Gulfton Lift Station, Linkwood Lift Station, Saddle Brook Lift Station, Alder Lift Station, Boonridge Lift Station) -Consent Decree   491F,530M,531A,531K,532N,571Z   $18,500,000.00   08-25-2027(s)   11-03-2027(s)      07-30-2028(s)   09-13-2028(s)   11-22-2028(s)                   
161  R-000267-0179-3   Lift Station Rehabilitation and Reconstruction Design (Lockwood Lift Station, South Point Lift Station, Scott #3 Lift Station, Market St. #2 Lift Station, M.U.D. #067 Lift Station, Woodforest Lift Station) - Consent Decree   494Q,497K,496D,576Q,573G,617B   $30,000,000.00   08-25-2027(s)   11-03-2027(s)      07-30-2028(s)   09-13-2028(s)   11-22-2028(s)                   
162  S-001000-56B2-3   LAS System at Ground Water Facilities and Chemical Improvements at Repump Stations - Package 3   488F,488L,374U,374A,374Y   $4,789,900.00   08-25-2027(s)   11-03-2027(s)   830   02-10-2030(s)   03-27-2030(s)   06-05-2030(s)                   
163  S-000035-0312-3   WLR in Second Ward North   493M,493R,494J,494R   $5,656,930.00   08-30-2027(s)   11-08-2027(s)      08-04-2028(s)   09-18-2028(s)   11-27-2028(s)                   
164  S-001000-056C-3   LAS System at Ground Water Facilities and Chemical Improvements at Repump Stations - Package 4   528B,530V,529C,490Y,528D,530H,530E,531X   $7,717,000.00   08-30-2028(s)   11-08-2028(s)   660   08-30-2030(s)   10-14-2030(s)   12-23-2030(s)                   
165  R-000035-0029-3   Force Main Rehabilitation and Reconstruction Projects - Consent Decree (Goodyear Lift Station, Scarsdale Lift Station)   616D,535M   $6,653,000.00   09-01-2027(s)   11-10-2027(s)   540   05-03-2029(s)   06-17-2029(s)   08-26-2029(s)                   
166  R-001000-0035-3   CRMP CIP Package 4 -Replacement of Eddington LS, FM Installation, and Construction of Storage Tank at Scott Street WWF.   494X,534B   $85,005,000.00   09-01-2027(s)   11-10-2027(s)      08-06-2028(s)   09-20-2028(s)   11-29-2028(s)                   
167  R-001000-0039-3   CRMP CIP Package 3 (CD Area 2 and 3)   494L   $470,000,000.00   09-11-2029(s)   11-20-2029(s)   1000   08-16-2032(s)   09-30-2032(s)   12-09-2032(s)                   
168  N-100030-003A-3   Antoine Drive Paving & Drainage: Acorn Street to US 290   451G,451L   $0.00   09-12-2029(s)   11-21-2029(s)      12-26-2030(s)   02-09-2031(s)   04-20-2031(s)                   
169  S-000012-032B-3   Southeast Water Purification Plant (SEWPP) Improvements Package 2   577R   $20,613,000.00   09-15-2027(s)   11-24-2027(s)      08-20-2028(s)   10-04-2028(s)   12-13-2028(s)                   
170  M-410024-0001-3   Southland Area Drainage and Paving Improvements Subproject 1   533G,533L,533Q      09-17-2025(p)   11-26-2025(p)      12-31-2026(p)   02-14-2027(p)   04-25-2027(p)   Prakash Luetel                
171  M-410013-0001-3   Melrose Park Sec 2 Drainage and Paving Improvements   413P,413Q,413T,413U   $22,571,777.30   09-20-2028(s)   11-29-2028(s)      01-03-2030(s)   02-17-2030(s)   04-28-2030(s)   Prakash Luetel                
172  N-100030-0001-3   Antoine (North) Paving and Drainage: Victory to West Gulf Bank   411Q,411U   $15,573,369.06   09-22-2027(s)   12-01-2027(s)      01-04-2029(s)   02-18-2029(s)   04-29-2029(s)                   
173  S-000035-0309-3   WLR in Memorial Neighborhood-Area A   489E,489A   $11,734,072.00   09-27-2027(s)   12-06-2027(s)      09-01-2028(s)   10-16-2028(s)   12-25-2028(s)                   
174  S-000600-060A-3   New Construction of One (1) Ground Water Storage Tank (GST) No. 2 at Moonshine Hill Water Plant and One (1) Hydropneumatic Tank (HPT) No. 2 at District 159 Water Plant    336T,370K   $0.00   09-29-2027(s)   12-08-2027(s)      09-03-2028(s)   10-18-2028(s)   12-27-2028(s)                   
175  N-T05000-0012-3   Waugh Dr and Heights Blvd Safety Improvements / City of Houston Systemic Safety Project (HSIP-24)      $0.00   09-30-2026(a)   12-09-2026(a)      01-13-2028(a)   02-27-2028(a)   05-07-2028(a)                   
176  N-100030-0GEC-3   General Engineering Consultant (GEC) for Antoine Drive from US 290 to W Mt Houston   411K,411L,411Q,411U,411Y,451C,451G,451L   $113,300,000.01   09-30-2026(p)   12-09-2026(p)      01-13-2028(p)   02-27-2028(p)   05-07-2028(p)                   
177  R-000265-0153-3   Keegans Bayou Wastewater Treatment Plant Improvements   530S   $45,050,000.00   10-06-2027(s)   12-15-2027(s)   720   12-04-2029(s)   01-18-2030(s)   03-29-2030(s)                   
178  S-000065-0012-3   Construction of New Monofil at Northeast Water Purification Plant (NEWPP)   377W   $45,383,732.00   10-06-2027(s)   12-15-2027(s)   724   12-08-2029(s)   01-22-2030(s)   04-02-2030(s)                   
179  S-000035-0314-3   WLR in Sunnyside Area   533Y,573C   $14,864,055.00   10-08-2027(s)   12-17-2027(s)      09-12-2028(s)   10-27-2028(s)   01-05-2029(s)                   
180  S-000901-0015-3   84-inch Water Line Repair and Condition Assessment from the Northeast Water Purification Plant to Smith Rd   375S,375T,375U,375V,375W,375X,375Y,375Z,376W,376X,376Y,376Z   $5,325,000.00   10-13-2027(s)   12-22-2027(s)   300   10-17-2028(s)   12-01-2028(s)   02-09-2029(s)   Panduranga Kuruva                
181  S-001000-56B1-3   LAS System at Ground Water Facilities and Chemical Improvements at Repump Stations - Package 2    488A,457C,487C,448W,447W   $4,335,000.00   10-13-2027(s)   12-22-2027(s)      09-17-2028(s)   11-01-2028(s)   01-10-2029(s)                   
182  S-000035-0324-3   WMR in Briargate and Willow Park Subdivisions      $0.00   10-16-2028(s)   12-25-2028(s)      09-21-2029(s)   11-05-2029(s)   01-14-2030(s)                   
183  N-900001-001A-3   New TDO Buildings at Various Locations: 8002 Airline Drive    413T   $0.00   10-18-2027(s)   12-27-2027(s)      01-30-2029(s)   03-16-2029(s)   05-25-2029(s)                   
184  N-900001-001B-3   New TDO Buildings at Various Locations: 5216 North McCarty Street   455U,455V   $0.00   10-18-2027(s)   12-27-2027(s)      01-30-2029(s)   03-16-2029(s)   05-25-2029(s)                   
185  N-32F782-0001-3   IMD Bikeways from Dairy Ashford Road to Arthur Storey Park   529J,529K,529L,528M   $0.00   10-18-2028(s)   12-27-2028(s)      01-31-2030(s)   03-17-2030(s)   05-26-2030(s)   Yusherry Cang                
186  R-000265-0166-3   Kingwood West Wastewater Treatment Plant Hazard Mitigation -FEMA-CD      $43,125,000.00   10-18-2028(s)   12-27-2028(s)      09-23-2029(s)   11-07-2029(s)   01-16-2030(s)                   
187  S-000900-0304-3   Groundwater Reduction Plan (GRP) Conversion Waterlines Group C   332Z,333W   $5,178,300.00   10-18-2028(s)   12-27-2028(s)      09-23-2029(s)   11-07-2029(s)   01-16-2030(s)   Panduranga Kuruva                
188  S-000035-0298-3   Waterline Replacement in Midtown Area   493P,493T,493U,493X,493V   $5,775,000.00   10-22-2026(s)   12-31-2026(s)   225   08-13-2027(s)   09-27-2027(s)   12-06-2027(s)