| No. |
WBS No. |
Project Name |
Status |
Council District |
Work Authorizations |
NTP |
Substantial Comp. Date |
MWBE Goal / %To Date |
Approx.Cons. Cost |
Remarks |
| 1 |
M-410035-0001-4
|
Northside High School Area Drainage and Paving |
Active |
H |
0 |
04/06/2026 |
05/30/2029 |
20% / 0.00% |
$40,994,635.06 |
10/16/2026]
The contractor is currently working on Panama and Booth streets as part of phases 1 and 2 of their phasing plan. The project is on schedule, and we are addressing issues with power risers and fence relocations. |
| 2 |
M-430006-0018-4
|
FY2022 Drainage Rehab (SWAT) Work Orders #3 |
Active |
A,B,C,D,E,F,G,H,I,J |
4 |
11/01/2022 |
|
20% / 20.00% |
$3,000,000.00 |
|
| 3 |
M-430006-0037-4
|
FY2025 Drainage Rehab (SWAT) Work Orders #4 |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
2 |
06/01/2026 |
|
20.00% / 0.00% |
$5,000,000.00 |
|
| 4 |
M-43M009-0013-4
|
FY 2025 Ditch Re-Establishment Work Order Contract # 5 |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
6 |
12/29/2025 |
|
23% / 0.00% |
$6,000,000.00 |
|
| 5 |
M-43M009-0014-4
|
FY 2026 Ditch Re-establishment (DRE) Work Order Contract # 1 |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
3 |
04/01/2026 |
03/01/2028 |
23% / 23.00% |
$8,000,000.00 |
|
| 6 |
N-000396-0015-4
|
Lorraine Grade Separation from Hardy Street to Jensen Drive |
Pending |
H |
0 |
|
|
0% / |
$0.01 |
|
| 7 |
N-000420-0030-4
|
MKT/SP Rails to Trails |
Pending |
H |
0 |
|
|
0% / |
$1.00 |
|
| 8 |
N-000670-0003-4
|
ILA - Harrisburg Overpass: at HBTRR Between Caylor St and 66th St. (Metro Solutions - East End Corridor Lite Rail System) |
Active |
H |
5 |
04/01/2015 |
|
0% / |
$0.01 |
Project isn't closed due funding discrepancies with Metro |
| 9 |
N-000700-0001-4
|
Collingsworth Grade Separation at Proposed Hardy Toll Road |
Pending |
B,H |
0 |
|
|
0% / |
$0.00 |
|
| 10 |
N-321040-0130-4
|
FY2025 Roadway Rehabilitation Project #2 |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
8 |
07/28/2025 |
|
20% / 0.00% |
$6,444,996.52 |
|
| 11 |
N-321040-0147-4
|
City of Houston Systemic Safety Project (HSIP-24) |
Pending |
A,C,D,H |
3 |
11/30/2026 |
|
0% / |
$2,210,463.06 |
[10.26.26] NOA issued to contractor on 10.23.26. Pre-con meeting to be held on 11.03.26 |
| 12 |
N-321040-0148-4
|
City of Houston Systemic Safety Project (HSIP-25) |
Active |
F,H,J |
2 |
04/27/2026 |
02/21/2027 |
0% / 0.00% |
$731,263.80 |
[11.05.26]
a/b) Current/Progress: St George WA#1 location - Contractor has installed the RRFBs, attempted to install overhead signals at Hillcroft but identified conflict with secondary conductor wires per RFI 11. EOR coordinating with Centerpoint for resolution. Crossing markings expected to be installed along with roadside signs as final step this month for all RRFB locations. Advisory Notice issued for water ponding at Skyline south side detectable warning surface area, spoke with Brizo today and he to reply to EOR proposed demo and raise solution. / White Oak at Greenleaf have installed RRFB and some roadside signs. Sidewalk demo and replacement with culvert and markings still pending. Brizo crew pulled for another job, awaiting schedule which may have them, back next week.
|
| 13 |
N-322017-0035-4
|
Citywide Work Orders for CDSF Project #14 |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
12 |
03/03/2025 |
|
20% / 30.00% |
$2,064,164.60 |
|
| 14 |
R-000266-0395-4
|
Wastewater Collection System Rehabilitation and Renewal |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
536 |
10/07/2025 |
|
0% / 0.00% |
$5,219,736.83 |
|
| 15 |
R-000266-0402-4
|
Wastewater Collection System Rehabilitation and Renewal |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
513 |
05/13/2026 |
|
20% / 0.00% |
$5,399,737.61 |
|
| 16 |
R-000266-0403-4
|
Wastewater Collection System Rehabilitation and Renewal |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
257 |
08/27/2026 |
|
0% / 0.00% |
$5,616,932.00 |
|
| 17 |
R-000267-0173-4
|
Braeswood N, Post Oak #2, Bissonnet #4, Brooklet, NE Sludge Transfer (Dorsett), and Synott Road #1 Lift Stations Renewal and Replacement Project |
Pending |
C,F,H,J,K |
0 |
|
|
0% / |
$0.00 |
|
| 18 |
R-000509-0027-4
|
69th st WWTP Pump Station, Digester and Thickener Blower Switchgears, Sub-Station and Starter Replacement |
Active |
H |
0 |
03/04/2014 |
|
18% / |
$11,995,692.45 |
|
| 19 |
R-000509-0039-4
|
69th Street WWTP Cleaning and Evaluation |
Active |
H |
0 |
08/28/2017 |
|
18% / |
$4,856,410.00 |
|
| 20 |
R-002015-0007-4
|
Work Order No. 2, Wastewater System/Substitute Service Support ¿ Sherman St. |
Active |
H |
0 |
08/19/2015 |
|
0% / |
$479,556.00 |
|
| 21 |
R-002015-0010-4
|
Work Order No. 5, Wastewater System/Substitute Service Support - Sherman St. Pkg. 2 |
Active |
H,I |
0 |
04/21/2016 |
|
0% / |
$368,700.00 |
|
| 22 |
R-002015-0012-4
|
Work Order No. 5, Wastewater System/Substitute Service Support, Bellaire West and Winlow Place |
Active |
C,D,F,H,I |
0 |
08/19/2015 |
|
0% / |
$511,545.00 |
|
| 23 |
R-002015-0020-4
|
Wastewater System/Substitute Service Support ¿ Beverly, Fugate (Work Order No. 1) |
Active |
C,H |
0 |
02/06/2017 |
|
0% / |
$375,000.00 |
|
| 24 |
R-002015-0035-4
|
New Front Easement Reconnections |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
122 |
04/23/2026 |
|
18% / 0.00% |
$2,643,753.10 |
|
| 25 |
S-000020-0082-4
|
On-Call Rehabilitation of Large Diameter Water Lines Package 2 |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
82 |
08/16/2023 |
12/18/2025 |
19% / 20.21% |
$2,500,000.00 |
|
| 26 |
S-000700-0084-4
|
Work Order Construction Contract for Small Diameter Water Lines (WO 17) |
Active |
C,D,H |
5 |
03/17/2025 |
03/17/2027 |
23% / 22.94% |
$4,375,000.00 |
08/24/2026
WO 5 , Contractor de mobilized. Utility co-ordination in progress to resolve RFI 2. AT&T agreed to relocate their conduit but takes 12-18 months to complete.
WO 4. Currently active. Service connections in progress |
| 27 |
S-000700-0090-4
|
MISC SDWL, FH, VALVE REHABILITATION AND REPAIR - PACKAGE 2 |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
2476 |
07/21/2025 |
|
23% / 23.31% |
$26,676,968.22 |
|
| 28 |
S-000700-0092-4
|
Misc SDWL, FH Valve Rehabilitation and Repair - Package III |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
746 |
09/17/2025 |
|
23% / 102.81% |
$6,657,363.58 |
|
| 29 |
S-000700-0093-4
|
Misc SDWL, FH and Valve rehab and Repairs - Package IV |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
710 |
10/28/2025 |
|
23% / 23.78% |
$4,445,470.65 |
|
| 30 |
S-000700-0094-4
|
Misc SDWL, FH, Valve Rehab & Repairs |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
1031 |
07/21/2025 |
|
17% / 39.48% |
$11,161,129.66 |
|
| 31 |
S-000700-0096-4
|
Misc SDWL, FH, Valve Rehab & Repairs |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
1546 |
05/09/2025 |
|
23% / 48.39% |
$10,290,000.00 |
|
| 32 |
S-000700-0098-4
|
Misc SDWL, FH, Valve Rehab & Repairs |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
1571 |
07/14/2025 |
|
23% / 23.86% |
$11,550,000.00 |
|
| 33 |
S-000700-0101-4
|
Work Order Construction Contract for Small Diameter Water Lines |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
2 |
06/08/2026 |
06/07/2028 |
23% / 0.00% |
$5,000,000.00 |
WO1:RFI 2 submitted by Reliance on 08/23/2026, EOR currently reviewing the RFI.
WO2: Contractor to mobilize on 08/24/2026. LoA issued on 08/12/2026 |
| 34 |
S-000700-0108-4
|
Misc. SDWL, FH, Valve Rehab & Repair |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
710 |
07/08/2026 |
|
23% / 0.00% |
$15,000,000.00 |
|
| 35 |
S-000701-0051-4
|
On-Call Rehabilitation of Large Diameter Water Lines Package 3 |
Active |
A,B,C,D,E,F,G,H,I,J,K,T |
75 |
07/21/2025 |
|
17% / 29.17% |
$4,000,000.00 |
|